Development Period     
 

The contract for the concession was signed on 7th May 2001.

The signing of the concession contract marked the start of a series of meetings and extensive communications between more than ten cities around the globe, though most of the meetings were held in Kuwait. Indeed, the total time spent during the 14-month development period, which ended on 7th July 2002, exceeded 300,000 man-hours.

During the development period, the basic design of the project was completed.

On 24th June 2002, a facility agreement was signed with National Bank of Kuwait, Gulf Bank, and the Bank of Kuwait and the Middle East. On the same date, the engineering, procurement and construction (EPC) contract, and the operation and maintenance contract which continues until the end of the concession, were also signed. 

On 7th July 2002, the Ministry of Public Works and Utilities Development Company jointly announced the commencement of the concession period and the start of construction.

 





 
 